Activities that must occur immediately before a given activity are called ________ activities.


A) predecessor
B) successor
C) prior
D) immediate
E) concurrent or parallel

F) B) and C)
G) C) and D)

Correct Answer

verifed

verified

Using free slack does not delay any following activities and requires no coordination with managers of other activities.

A) True
B) False

Correct Answer

verifed

verified

Consider the following table of activities A through G in which A is the start node and G is the stop node.


A) 26
B) 27
C) 28
D) 29
E) 30

F) C) and D)
G) B) and D)

Correct Answer

verifed

verified

What is a hammock activity and give an example?

Correct Answer

verifed

verified

A hammock activity identifies the use of...

View Answer

On a piece of scratch paper, draw an early-start Gantt Chart for the following table. What does a Gantt Chart tell you that a network chart does not?

Correct Answer

verifed

verified

The Gantt Chart, because its h...

View Answer

Consider the following table of activities A through G in which A is the start node and G is the stop node.


A) Non-critical activity
B) Critical activity
C) Merge activity
D) Burst activity
E) Both critical activity and merge activity

F) All of the above
G) A) and B)

Correct Answer

verifed

verified

When completing a backward pass, you carry the LS to the next preceding activity to establish the LF, unless the next preceding activity is a burst activity, in which case you select


A) the smallest LS of all its immediate successor activities to establish the LF.
B) the largest ES of all its immediate successor activities to establish the LF.
C) the average LS of all its immediate successor activities to establish the LF.
D) the smallest ES of all its immediate successor activities to establish the LF.
E) the largest LS of all its immediate successor activities to establish the LF.

F) A) and E)
G) B) and E)

Correct Answer

verifed

verified

In a project network, ________ indicate activity dependency and project flow.


A) nodes
B) arrows
C) boxes
D) labels
E) slacks

F) A) and B)
G) C) and E)

Correct Answer

verifed

verified

Which of the following can be used without coordinating with managers of succeeding activities?


A) Total slack
B) Free slack
C) Critical float
D) Float pad
E) Slip pad

F) C) and D)
G) A) and E)

Correct Answer

verifed

verified

A(n) _____________ calculates how late an activity can start and finish.


A) forward pass
B) backward pass
C) circular pass
D) complete enumeration
E) late finish

F) A) and E)
G) C) and D)

Correct Answer

verifed

verified

On a project network, the activity times are derived from the


A) organization breakdown structure.
B) work packages.
C) budget.
D) project proposal.
E) responsibility matrix.

F) A) and D)
G) B) and C)

Correct Answer

verifed

verified

The assumption that all immediately preceding activities must be 100% complete is too restrictive in some situations. When an activity is broken down into smaller segments in order to start the succeeding activity sooner, this is called


A) hammock activities.
B) concurrent engineering.
C) a forward pass.
D) dissecting.
E) laddering.

F) B) and C)
G) None of the above

Correct Answer

verifed

verified

When creating a project network, your primary input source will be the


A) project charter.
B) work packages.
C) risk plan.
D) communication plan.
E) requirements document.

F) C) and E)
G) A) and E)

Correct Answer

verifed

verified

Consider the following table of activities A through G in which A is the start node and G is the stop node.


A) Cannot be determined
B) Project duration would increase by two days.
C) Project duration would remain the same.
D) Project duration would decrease by two days.
E) Project duration would increase by four days.

F) D) and E)
G) B) and E)

Correct Answer

verifed

verified

Which of the following is provided by both the project network and the work breakdown structure?


A) Dependencies
B) Sequencing
C) Interrelationships
D) Activity duration
E) Timing

F) A) and B)
G) C) and D)

Correct Answer

verifed

verified

Which of the following correctly calculates the early finish for an activity?


A) LS + DUR
B) ES + DUR
C) LF + DUR
D) ES + SL
E) LF + SL

F) A) and B)
G) A) and C)

Correct Answer

verifed

verified

An activity can include only one work package.

A) True
B) False

Correct Answer

verifed

verified

In a project network, recycling through a set of activities or __________ is not permitted.


A) looping
B) forward pass
C) backward pass
D) circular pass
E) late finish

F) B) and D)
G) B) and C)

Correct Answer

verifed

verified

Experience suggests that when there are multiple starts, a common start node should be used to indicate a clear project beginning on the network. Similarly, a single project end node can be used to indicate a clear ending.

A) True
B) False

Correct Answer

verifed

verified

Activities that can occur while another activity is taking place are called ________ activities.


A) predecessor
B) successor
C) prior
D) immediate
E) concurrent or parallel

F) C) and D)
G) A) and E)

Correct Answer

verifed

verified