A) predecessor
B) successor
C) prior
D) immediate
E) concurrent or parallel
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) 26
B) 27
C) 28
D) 29
E) 30
Correct Answer
verified
Essay
Correct Answer
verified
View Answer
Essay
Correct Answer
verified
View Answer
Multiple Choice
A) Non-critical activity
B) Critical activity
C) Merge activity
D) Burst activity
E) Both critical activity and merge activity
Correct Answer
verified
Multiple Choice
A) the smallest LS of all its immediate successor activities to establish the LF.
B) the largest ES of all its immediate successor activities to establish the LF.
C) the average LS of all its immediate successor activities to establish the LF.
D) the smallest ES of all its immediate successor activities to establish the LF.
E) the largest LS of all its immediate successor activities to establish the LF.
Correct Answer
verified
Multiple Choice
A) nodes
B) arrows
C) boxes
D) labels
E) slacks
Correct Answer
verified
Multiple Choice
A) Total slack
B) Free slack
C) Critical float
D) Float pad
E) Slip pad
Correct Answer
verified
Multiple Choice
A) forward pass
B) backward pass
C) circular pass
D) complete enumeration
E) late finish
Correct Answer
verified
Multiple Choice
A) organization breakdown structure.
B) work packages.
C) budget.
D) project proposal.
E) responsibility matrix.
Correct Answer
verified
Multiple Choice
A) hammock activities.
B) concurrent engineering.
C) a forward pass.
D) dissecting.
E) laddering.
Correct Answer
verified
Multiple Choice
A) project charter.
B) work packages.
C) risk plan.
D) communication plan.
E) requirements document.
Correct Answer
verified
Multiple Choice
A) Cannot be determined
B) Project duration would increase by two days.
C) Project duration would remain the same.
D) Project duration would decrease by two days.
E) Project duration would increase by four days.
Correct Answer
verified
Multiple Choice
A) Dependencies
B) Sequencing
C) Interrelationships
D) Activity duration
E) Timing
Correct Answer
verified
Multiple Choice
A) LS + DUR
B) ES + DUR
C) LF + DUR
D) ES + SL
E) LF + SL
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) looping
B) forward pass
C) backward pass
D) circular pass
E) late finish
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) predecessor
B) successor
C) prior
D) immediate
E) concurrent or parallel
Correct Answer
verified
Showing 81 - 100 of 128
Related Exams